Week 6 Assignment – Project Tasks and TimelineInstructions:Carefully look through the "Sample" tab. Pay close attention to the amount of detail included, and the formatting and organization of the list. You will use this sample list as a guide to create your own list of tasks, but you should not duplicate the content from the sample exactly.Navigate to the third tab titled, "Blank Template – Fill This In" and complete the following:1. In the “Activity” column, outline a plausible list of tasks needed to complete your chosen project. You may group tasks together as in the Sample tab, or list each task separately.2. In the “Start Date”, “End Date”, and “Days to Complete” columns, estimate plausible timelines for each task or group of tasks. In the first row, highlighted in yellow, give a start and end date for the project as a whole.
tc={E7F4959B-F80D-4A4D-B776-698FBD452113}: [Threaded comment]Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924Comment: Recommend adding language to clearly point out that the three tabs are at the bottom and that they are not to duplicate the content from the sample.

Sample

Project Tasks and TimelineDeveloped by John SmithOctober 2022
Activity Days to Complete Start Date End Date
Construction Plan 253 Saturday, January 1, 2022 Sunday, September 11, 2022
Planning Activites 30 Saturday, January 1, 2022 Monday, January 31, 2022
Finalize Plans
Sign Contract to Proceed
Construction Activities 45 Monday, January 31, 2022 Thursday, March 17, 2022
Prepare Site
Prepare Foundation for Property
Establish Framing for Property
Exterior Work Activities 30 Thursday, March 17, 2022 Saturday, April 16, 2022
Install Roof
Install Windows
Install Doors
Install Bricks
Install Siding
Interior Work Activities 120 Saturday, April 16, 2022 Sunday, August 14, 2022
Install Insulation
Install Drywall
Install Plumbing & Related Fixtures
Install Electrical & Related Fixtures
Install HVAC
Install Cabinets
Install Flooring
Install Appliances
Grounds Work Activities 14 Sunday, August 14, 2022 Sunday, August 28, 2022
Install Driveway
Install Sidewalks
Install Fencing
Install Deck
Lay Sod & Plants
Final Acceptance 14 Sunday, August 28, 2022 Sunday, September 11, 2022
Clean Up Property for Inspection (Cleaning Service)
Inspection by Local Government
Address Issues from Government Inspection
Inspection by Owner
Address Issues from Owner Inspection
Turn Property Over to Owner

Blank Sheet

Construction Progress ReportName: Tyrell WilsonDate: 11/28/2022
Activity Days to Complete Start Date End Date
Construction Plan 253 Tuesday, February 1, 2022 Wednesday, October 12, 2022
Planning Activites 30 Tuesday, February 1, 2022 Wednesday, March 2, 2022
Finalize Plans 28 Tuesday, February 1, 2022 Monday, February 28, 2022
Sign Contract to Proceed 2 Monday, Feburary 28, 2022 Wednesday, March 2, 2022
Construction Activities 45 Wednesday, March 2, 2022 Saturday, April 16, 2022
Prepare Site 7 Wednesday, March 2, 2022 Wednesday, March 9, 2022
Prepare Foundation for Property 13 Wednesday, March 9, 2022 Tuesday, March 22, 2022
Establish Framing for Property 25 Tuesday, March 22, 2022 Saturday, April 16, 2022
Exterior Work Activities 30 Saturday, April 16, 2022 Monday, May 16, 2022
Install Roof 7 Saturday, April 16, 2022 Saturday, April 23, 2022
Install Windows 1 Saturday, April 23, 2022 Sunday, April 24, 2022
Install Doors 1 Monday, April 25, 2022 Tuesday, April 26, 2022
Install Bricks 6 Tuesday, April 26, 2022 Monday, May 2, 2022
Install Siding 14 Monday, May 2, 2022 Monday, May 16, 2022
Interior Work Activities 120 Monday, May 16, 2022 Tuesday, September 13, 2022
Install Insulation 15 Monday, May 16, 2022 Tuesday, May 31, 2022
Install Drywall 15 Tuesday, May 31, 2022 Thursday, June 14, 2022
Install Plumbing & Related Fixtures 15 Thursday, June 14, 2022 Wednesday, June 29, 2022
Install Electrical & Related Fixtures 15 Wednesday, June 29, 2022 Thursday, July 14, 2022
Install HVAC 15 Thursday, July 14, 2022 Friday, July 29, 2022
Install Cabinets 15 Friday, July 29, 2022 Saturday, August 13, 2022
Install Flooring 15 Saturday, August 13, 2022 Sunday, August 28, 2022
Install Appliances 15 Sunday, August 28, 2022 Monday, September 12, 2022
Grounds Work Activities 15 Monday, September 12, 2022 Tuesday, September 27, 2022
Install Driveway 3 Monday, September 12, 2022 Monday, September 15, 2022
Install Sidewalks 3 Monday, September 15, 2022 Sunday, September 18, 2022
Install Fencing 3 Sunday, September 18, 2022 Wednesday, September 21, 2022
Install Deck 3 Wednesday, September 21, 2022 Saturday, September 24, 2022
Lay Sod & Plants 3 Saturday, September 24, 2022 Tuesday, September 27, 2022
Final Acceptance 14 Tuesday, September 27, 2022 Wednesday, October 12, 2022
Clean Up Property for Inspection (Cleaning Service) 4 Wednesday, September 28, 2022 Sunday, October 2, 2022
Inspection by Local Government 2 Sunday, October 2, 2022 Tuesday, October 4, 2022
Address Issues from Government Inspection 2 Tuesday, October 4, 2022 Thursday, October 6, 2022
Inspection by Owner 2 Thursday, October 6, 2022 Saturday, October 8, 2022
Address Issues from Owner Inspection 2 Saturday, October 8, 2022 Monday, October 10, 2022
Turn Property Over to Owner 2 Monday, October 10, 2022 Wednesday, October 12, 2022