Week 6 Assignment – Project Tasks and TimelineInstructions:Carefully look through the "Sample" tab. Pay close attention to the amount of detail included, and the formatting and organization of the list. You will use this sample list as a guide to create your own list of tasks, but you should not duplicate the content from the sample exactly.Navigate to the third tab titled, "Blank Template – Fill This In" and complete the following:1. In the “Activity” column, outline a plausible list of tasks needed to complete your chosen project. You may group tasks together as in the Sample tab, or list each task separately.2. In the “Start Date”, “End Date”, and “Days to Complete” columns, estimate plausible timelines for each task or group of tasks. In the first row, highlighted in yellow, give a start and end date for the project as a whole. tc={E7F4959B-F80D-4A4D-B776-698FBD452113}: [Threaded comment]Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924Comment: Recommend adding language to clearly point out that the three tabs are at the bottom and that they are not to duplicate the content from the sample. |
Sample
Project Tasks and TimelineDeveloped by John SmithOctober 2022 | |||
Activity | Days to Complete | Start Date | End Date |
Construction Plan | 253 | Saturday, January 1, 2022 | Sunday, September 11, 2022 |
Planning Activites | 30 | Saturday, January 1, 2022 | Monday, January 31, 2022 |
Finalize Plans | |||
Sign Contract to Proceed | |||
Construction Activities | 45 | Monday, January 31, 2022 | Thursday, March 17, 2022 |
Prepare Site | |||
Prepare Foundation for Property | |||
Establish Framing for Property | |||
Exterior Work Activities | 30 | Thursday, March 17, 2022 | Saturday, April 16, 2022 |
Install Roof | |||
Install Windows | |||
Install Doors | |||
Install Bricks | |||
Install Siding | |||
Interior Work Activities | 120 | Saturday, April 16, 2022 | Sunday, August 14, 2022 |
Install Insulation | |||
Install Drywall | |||
Install Plumbing & Related Fixtures | |||
Install Electrical & Related Fixtures | |||
Install HVAC | |||
Install Cabinets | |||
Install Flooring | |||
Install Appliances | |||
Grounds Work Activities | 14 | Sunday, August 14, 2022 | Sunday, August 28, 2022 |
Install Driveway | |||
Install Sidewalks | |||
Install Fencing | |||
Install Deck | |||
Lay Sod & Plants | |||
Final Acceptance | 14 | Sunday, August 28, 2022 | Sunday, September 11, 2022 |
Clean Up Property for Inspection (Cleaning Service) | |||
Inspection by Local Government | |||
Address Issues from Government Inspection | |||
Inspection by Owner | |||
Address Issues from Owner Inspection | |||
Turn Property Over to Owner |
Blank Sheet
Construction Progress ReportName: Tyrell WilsonDate: 11/28/2022 | |||
Activity | Days to Complete | Start Date | End Date |
Construction Plan | 253 | Tuesday, February 1, 2022 | Wednesday, October 12, 2022 |
Planning Activites | 30 | Tuesday, February 1, 2022 | Wednesday, March 2, 2022 |
Finalize Plans | 28 | Tuesday, February 1, 2022 | Monday, February 28, 2022 |
Sign Contract to Proceed | 2 | Monday, Feburary 28, 2022 | Wednesday, March 2, 2022 |
Construction Activities | 45 | Wednesday, March 2, 2022 | Saturday, April 16, 2022 |
Prepare Site | 7 | Wednesday, March 2, 2022 | Wednesday, March 9, 2022 |
Prepare Foundation for Property | 13 | Wednesday, March 9, 2022 | Tuesday, March 22, 2022 |
Establish Framing for Property | 25 | Tuesday, March 22, 2022 | Saturday, April 16, 2022 |
Exterior Work Activities | 30 | Saturday, April 16, 2022 | Monday, May 16, 2022 |
Install Roof | 7 | Saturday, April 16, 2022 | Saturday, April 23, 2022 |
Install Windows | 1 | Saturday, April 23, 2022 | Sunday, April 24, 2022 |
Install Doors | 1 | Monday, April 25, 2022 | Tuesday, April 26, 2022 |
Install Bricks | 6 | Tuesday, April 26, 2022 | Monday, May 2, 2022 |
Install Siding | 14 | Monday, May 2, 2022 | Monday, May 16, 2022 |
Interior Work Activities | 120 | Monday, May 16, 2022 | Tuesday, September 13, 2022 |
Install Insulation | 15 | Monday, May 16, 2022 | Tuesday, May 31, 2022 |
Install Drywall | 15 | Tuesday, May 31, 2022 | Thursday, June 14, 2022 |
Install Plumbing & Related Fixtures | 15 | Thursday, June 14, 2022 | Wednesday, June 29, 2022 |
Install Electrical & Related Fixtures | 15 | Wednesday, June 29, 2022 | Thursday, July 14, 2022 |
Install HVAC | 15 | Thursday, July 14, 2022 | Friday, July 29, 2022 |
Install Cabinets | 15 | Friday, July 29, 2022 | Saturday, August 13, 2022 |
Install Flooring | 15 | Saturday, August 13, 2022 | Sunday, August 28, 2022 |
Install Appliances | 15 | Sunday, August 28, 2022 | Monday, September 12, 2022 |
Grounds Work Activities | 15 | Monday, September 12, 2022 | Tuesday, September 27, 2022 |
Install Driveway | 3 | Monday, September 12, 2022 | Monday, September 15, 2022 |
Install Sidewalks | 3 | Monday, September 15, 2022 | Sunday, September 18, 2022 |
Install Fencing | 3 | Sunday, September 18, 2022 | Wednesday, September 21, 2022 |
Install Deck | 3 | Wednesday, September 21, 2022 | Saturday, September 24, 2022 |
Lay Sod & Plants | 3 | Saturday, September 24, 2022 | Tuesday, September 27, 2022 |
Final Acceptance | 14 | Tuesday, September 27, 2022 | Wednesday, October 12, 2022 |
Clean Up Property for Inspection (Cleaning Service) | 4 | Wednesday, September 28, 2022 | Sunday, October 2, 2022 |
Inspection by Local Government | 2 | Sunday, October 2, 2022 | Tuesday, October 4, 2022 |
Address Issues from Government Inspection | 2 | Tuesday, October 4, 2022 | Thursday, October 6, 2022 |
Inspection by Owner | 2 | Thursday, October 6, 2022 | Saturday, October 8, 2022 |
Address Issues from Owner Inspection | 2 | Saturday, October 8, 2022 | Monday, October 10, 2022 |
Turn Property Over to Owner | 2 | Monday, October 10, 2022 | Wednesday, October 12, 2022 |